Twenty five per cent work of Ambedkar memorial complete: Shinde

Maharashtra Urban Development Minister Eknath Shinde on Wednesday informed the state Legislative Council that 25 per cent work on the Ambedkar memorial in central Mumbai has been completed.

Shinde gave this information in a written reply. “Of the total work, around 25 per cent is complete.

MMRDA (Mumbai Metropolitan Region Development Authority) had planned expenditure of Rs 160 crore (for the memorial) during fiscal 2019-20,” he said.

“So far, Rs 124.58 crore have been spent,” the reply stated, adding that the construction would be completed by April 2022.

The memorial, with estimated cost of Rs 1,089.95 crore, is coming up at Indu Mills premises in Dadar area. It will include a 136.68 meter statue of the Dalit icon and architect of the Indian Constitution. – PTI 

Subscribe to TheNews21

Stay Ahead with Independent Journalism

Investigations, political analysis and major national and global stories delivered directly to your inbox.

Stay Ahead with Independent Journalism

Investigations, political analysis and major national and global stories delivered directly to your inbox.

42 COMMENTS

  1. Connect the millions friendly strapping on fanduel casino michigan – the #1 legitimate pelf casino app in America.
    Reach your $1000 TEASE IT AGAIN hand-out and turn every spin, хэнд and roll into official cash rewards.
    Firm payouts, gigantic jackpots, and continuous effect – download FanDuel Casino now and start playing like a pro today!

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Must Read

spot_img

Html code here! Replace this with any non empty text and that's it.

Must Read

spot_img