Srinagar: The augmentation of the capacity of power grid station at Delina in Baramulla will be completed by this month end. This in turn will significantly enhance the power supply position to Baramulla and Kupwara districts and bring relief to the people of the two districts. With this augmentation, the capacity of Delina Grid Station would double from existing 160 MVA to 320 MVA.
This was decided in a review meeting chaired by Rohit Kansal, Principal Secretary to Government, and Power Development Department (PDD) at Kupwara. Kansal was on a day-long extensive tour of Baramulla and Kupwara.
Later in the day, the Principal Secretary visited the Grid Station, Delina and took stock of 160 MV augmentation project. He complimented the engineers and staff for the efforts and exhorted them to complete the work by this Dec 31.
In another significant decision, it was decided that a 10.5 MW small hydroelectric project would be constructed at Mohra, Baramulla. Secretary PDD said that Mohra Hydro-Electric Project (HEP) shall be taken up for construction by J&K Power Development Corporation (JKPDC) and the work is expected to be allotted as early as March 2021.
Also Read: JK Zamindar forum wants Dr Abdullah to pledge in writing on bringing back Article 370
Mohra Power House bears great significance from a heritage point of view as it was the first hydroelectric project set up in J&K in the year 1905. The hydro-electric project would not only generate electricity but also revive and rekindle the old memories of the heritage Mohra Power House.
Earlier in the day, the Principal Secretary to Government, also reviewed in detail the power scenario of two remote districts of Kupwara and Baramulla and issued directions to the engineering staff to streamline the power system and remove the difficulties by taking additional measures.
He called upon all the officers to ensure that there is proper and swift mechanism in place for replacement and repair of damaged transformers and that damaged transformers are replaced immediately from the buffer stock kept available in all districts. He also emphasized that the damaged transformers must be repaired at the designated departmental workshops in the quickest time possible.
Instructions were given for quick transportation of damaged transformers from districts to the workshops twice a week to replenish the buffer stock and improve the turn- around and repair time of transformers. In order to improve the schedule of repair of damaged transformers, he also sanctioned two trunk-mounted cranes, one each for Kupwara and Sopore.
The Principal Secretary also gave directions to augment the capacity of the district level workshops so that 400KVA transformers are also repaired without referral to the Central workshop. He further stated that the overall objective of the department is to minimize the power outages during winters so that the people do not face inconvenience.
Reviewing the progress of on-going works, the Principal Secretary asked the engineers to complete all on-going projects under languishing projects head by Feb 15, 2021. He also directed that the projects under the Deen Dayal Upadhyay Gram Jyoti Yojana (DDUGJY) and Prime Minister Development Package – Urban (PMDP–U) must be completed by end of March 2021 in all towns and immediately handed over to the distribution corporation for installation of meters in these towns to achieve the target of 100% metering.
The Principal Secretary to Government also instructed the department officials to attend to the grievances and demands of the general public received through the call-centre set up by the Power Development Department.
The meeting also reviewed the revenue realization in the twin districts and the engineers and other field staff was directed to improve revenue realization and to take action against wilful defaulters. Instructions were given for improving billing efficiency and taking action for non-payment of dues against habitual offenders.
Later Rohit Kansal inspected the on-going construction work of the 33/11 KV Galizo Kupwara, Sub Station being constructed under the Integrated Power Development Scheme (IPDS/PMDP) Project. On the occasion, the Principal Secretary was informed that the Project is being constructed at a cost of Rs 4.28 Cr and shall be completed by January 31 2021. He was further informed that after Commissioning of the Project, it will relieve load on Tikker station and improve power supply in the district.