76 pc work of Mumbai Trans-harbour Link project completed: MMRDA

@the_news_21

Nearly 76 per cent work of the Mumbai Trans-Harbour Link (MTHL) project has been done so far and the plan is to complete the work by the end of September 2023, the Mumbai Metropolitan Region Development Authority (MMRDA) has said.

The MMRDA, a Maharashtra government agency, is the implementing authority for the 21.8 km six-lane MTHL project, financed by the Japan International Cooperation Agency (JICA).

When completed, it would be the longest sea bridge in India and would cater to 70,000 vehicles daily.

Maharashtra’s Tourism and Environment Minister Aaditya Thackeray recently reviewed the progress of the project by visiting the site in Sewri area here.

According to a release issued by the MMRDA on Monday, the work of MTHL is in progress in three different phases.

Out of six interchanges of the MTHL at Sewri, the work of C-2, ramp have been completed up to sub base and also the work of the 4 km of spread up to the deck slab of original bridge from this access road, have been completed, it said.

Since the work of 4 km spread of C-2 access road of the original bridge is completed, the contractor will be able to transport construction materials from the access road to the original bridge work, which will speed up the project construction, the release said.

Earlier, temporary bridges and elevators were used for bridge work and inspection, it noted.

“This is a milestone as it is currently possible to drive on the main bridge of MTHL on the roads of Mumbai,” the MMRDA said.

Subscribe to TheNews21

Stay Ahead with Independent Journalism

Investigations, political analysis and major national and global stories delivered directly to your inbox.

Stay Ahead with Independent Journalism

Investigations, political analysis and major national and global stories delivered directly to your inbox.

41 COMMENTS

  1. Upon the millions delightful strapping on fanduel casino Michigan – the #1 natural money casino app in America.
    Respite c start your $1000 PLAY IT AGAIN hand-out and deny b decrease every relate, hand and roll into bona fide cash rewards.
    Firm payouts, gigantic jackpots, and non-stop action – download FanDuel Casino any longer and start playing like a pro today!

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Must Read

spot_img

@the_news_21

Nearly 76 per cent work of the Mumbai Trans-Harbour Link (MTHL) project has been done so far and the plan is to complete the work by the end of September 2023, the Mumbai Metropolitan Region Development Authority (MMRDA) has said.

The MMRDA, a Maharashtra government agency, is the implementing authority for the 21.8 km six-lane MTHL project, financed by the Japan International Cooperation Agency (JICA).

When completed, it would be the longest sea bridge in India and would cater to 70,000 vehicles daily.

Maharashtra’s Tourism and Environment Minister Aaditya Thackeray recently reviewed the progress of the project by visiting the site in Sewri area here.

According to a release issued by the MMRDA on Monday, the work of MTHL is in progress in three different phases.

Out of six interchanges of the MTHL at Sewri, the work of C-2, ramp have been completed up to sub base and also the work of the 4 km of spread up to the deck slab of original bridge from this access road, have been completed, it said.

Since the work of 4 km spread of C-2 access road of the original bridge is completed, the contractor will be able to transport construction materials from the access road to the original bridge work, which will speed up the project construction, the release said.

Earlier, temporary bridges and elevators were used for bridge work and inspection, it noted.

“This is a milestone as it is currently possible to drive on the main bridge of MTHL on the roads of Mumbai,” the MMRDA said.

Html code here! Replace this with any non empty text and that's it.

41 COMMENTS

  1. Upon the millions delightful strapping on fanduel casino Michigan – the #1 natural money casino app in America.
    Respite c start your $1000 PLAY IT AGAIN hand-out and deny b decrease every relate, hand and roll into bona fide cash rewards.
    Firm payouts, gigantic jackpots, and non-stop action – download FanDuel Casino any longer and start playing like a pro today!

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Must Read

spot_img