Kolkata:The 1996 India–Bangladesh treaty on sharing the Ganga/Ganges waters at Farakka reaches the end of its 30-year term on 12 December 2026. The agreement replaced earlier short-term arrangements with a formula for sharing dry-season flows. Now, with the deadline approaching, Bangladesh is calling for a new or revised agreement that includes a guarantee for its water share. India has said river-related issues belong in the bilateral Joint Rivers Commission (JRC), while technical-level meetings continue. No agreed replacement treaty has been announced.
The question is not simply whether the two governments will renew the existing text. They must decide whether to retain its allocation formula, amend parts of it or negotiate a new framework. Each option will require agreement on how to manage low flows, exchange data and address changing conditions in the basin.
What the treaty provides
The treaty covers the five-month dry-season period from 1 January to 31 May. Its sharing formula divides the available flow at Farakka in three bands: when the flow is 70,000 cusecs or less, India and Bangladesh receive equal shares; between 70,000 and 75,000 cusecs, Bangladesh receives 35,000 cusecs and India takes the balance; at 75,000 cusecs or more, India receives 40,000 cusecs and Bangladesh takes the balance.
The formula includes a provision for alternating flows during part of the dry season. Annexure I says each country is to receive 35,000 cusecs in alternate periods during the period from 1 March to 10 May. Annexure II illustrates how the formula would work if flows matched average availability recorded at Farakka between 1949 and 1988. The treaty calls on the upper riparian to make every effort to protect flows at those historical levels; the schedule is not a guarantee that those flows will occur every year.
The text also requires immediate consultations if flows at Farakka fall below 50,000 cusecs in any 10-day period, so the governments can make emergency adjustments. It does not set a fixed minimum flow for such circumstances. Article XI addresses a different situation: if the parties fail to agree on adjustments following the periodic reviews described in Article X, India is to release downstream at least 90 per cent of Bangladesh’s share under the formula until mutually agreed flows are decided. That provision applies during the treaty period; it is not a general low-flow guarantee.
The treaty’s Joint Committee monitors its implementation, with teams at Farakka and Hardinge Bridge recording flows. If the committee cannot resolve a dispute, Article VII provides for referral to the JRC and, if needed, the two governments. The JRC is the wider bilateral institution for shared-river issues; it should not be confused with the treaty’s Joint Committee.
The status of talks
Indian parliamentary answers offer a dated account of the formal renewal process. In August 2025, the Ministry of External Affairs said bilateral discussions on renewal had not begun, while noting that India had consulted stakeholders, including West Bengal. In February 2026, the ministry again said formal renewal discussions had yet to commence and listed inter-ministerial consultations with West Bengal. Those answers describe the position at the time they were given; they do not establish the status of talks later in 2026.
Technical engagement has continued. Press reports said delegations met in Kolkata in May and visited Farakka as part of monitoring activity. In September, Bangladesh’s Water Resources Minister Shahiduddin Chowdhury Anee said Dhaka wanted a new treaty with a guarantee clause. Bangladesh’s foreign minister later told Parliament that a team had been formed to prepare a proposal and that Dhaka was awaiting an Indian response, according to The Business Standard.
India’s public position, as reported on 9 October, was that river-related matters would be discussed through the JRC. External Affairs Ministry spokesperson Randhir Jaiswal also referred to continuing technical-level meetings on the Ganges. On 15 October, Anee said the JRC was working on a fresh agreement with guarantee clauses. These statements point to continued engagement, but the public record does not yet show an agreed draft treaty or settled terms.
What Bangladesh wants—and what remains to be negotiated
Dhaka has made the guarantee clause a central demand. Anee has called for a new or revised agreement that secures Bangladesh’s dry-season share. He has also raised the issue of excessive monsoon flows. State Minister for Foreign Affairs Humaiun Kobir has said Bangladesh will seek an outcome that protects its national interests and that the country’s committee is ready to engage with Indian counterparts. These are stated negotiating priorities; they are not yet agreed provisions.
Bangladesh has pointed to the 1977 agreement, which included an 80 per cent safeguard for its scheduled share when flows fell below a specified level. The 1996 treaty adopted a different structure: a formula based on available flows, emergency consultations below 50,000 cusecs and the conditional Article XI provision. Any renewed agreement would need to specify exactly how a proposed guarantee would work—what flow it applies to, how it is measured, what happens in exceptionally dry periods and how the parties would respond if the threshold is not met.
For India, any revision would involve its own water-management considerations and input from relevant states. The 2025 and 2026 parliamentary replies confirm that West Bengal was consulted. Claims about specific state requirements or the effects of Farakka on flooding, sediment or port navigation should be treated cautiously unless tied to clearly identified technical studies or official submissions. The available treaty text alone does not settle those questions.
Three routes before the governments
The first option is renewal by mutual consent, as allowed under Article XII. This could preserve the current formula and monitoring arrangements, giving both sides continuity while leaving room for agreed changes. The treaty does not, however, provide an automatic extension.
The second option is a targeted revision. The governments could retain the central sharing formula while updating provisions on low-flow conditions, measurement, data exchange or review procedures. Such a route would require detailed agreement on the revised terms and the way they would operate in practice.
The third option is a new agreement with a wider scope. It could address additional aspects of water cooperation, but expanding the negotiations would also add issues to resolve before the deadline. The choice among these paths belongs to the two governments; the public statements so far do not establish which route they will take.
Article XII says the treaty remains in force for 30 years and is renewable by mutual consent. The 1996 text does not set out an automatic extension if no agreement is reached. What legal and operational arrangements would apply after its term ends without a renewal or interim agreement is not resolved by the text itself and should not be presumed. The governments would need to address continuity through their negotiations and any legal instruments they agree.
The case for a workable agreement
The treaty’s value lies in the predictable process it established: a defined sharing formula, joint flow monitoring and a route for raising unresolved disputes. Its approaching deadline gives India and Bangladesh an opportunity to assess how those mechanisms have worked and what changes, if any, both sides can accept.
For a renewed framework to be credible, it would need clear rules for normal and low-flow periods, transparent joint measurement and a defined process for responding when the parties disagree. Updating the data-sharing and review arrangements could also help negotiators distinguish disagreements about the formula from disagreements about measured flows.
The deadline is close, and Dhaka has publicly called for a guarantee clause while New Delhi has pointed to the JRC as the forum for river issues. Whether the talks produce a simple renewal, a revised treaty or an interim arrangement will depend on the terms both governments are prepared to accept. For now, the clearest measure of progress will be evidence of an agreed negotiating process and specific proposals—not statements of intent alone.